Point name |
Dornum |
Network operator |
Statoil Deutschland Transport GmbH |
Market area |
GASPOOL |
Adjacent network operator |
Gassco AS |
Direction |
Entry |
Min. pressure |
83,20 bar |
Max. pressure |
84,00 bar |
Gross calorific value: |
11,5 kWh/m³ |
Information on technical capacities |
The information on the technical capacity of the entry point result from its historic use and on the application of a statistical capacity model. |
Grid connection guidelines:
The connection guidelines of Open Grid Europe GmbH (OGE) apply for the pipeline subsection from Dornum to Wardenburg and the guidelines of Gasunie Deutschland Transport Services GmbH (GUD) apply for the pipeline subsection from Wardenburg to Steinitz.
Physical flows:
Due to a pipeline joint venture, the physical flows at the network point Dornum can not be published seperatly by TSOs. On the website of Open Grid Europe you can find the physical flows for the network point Dornum (www.open-grid-europe.de).